Extensions of time

Delays are common within construction projects and need to be administered efficiently. These delays might come from issues over which the employer has control, for example, handing over possession of the site, or neutral causes such as exceptionally adverse weather conditions.

In all cases the contractor must apply for, and be granted, an extension of time. This releases the contractor from delay damages for the period of the delay to completion.

The calculation of the payment of any additional costs caused by the delay is completely separate and is not dependent on the extension of time calculation.

This section is maintained by Jonathan Gaskell of law firm DLA Piper UK LLP