Example structure for a final account

Provisional sums

The project comprises a £5m educational building. The scheme was tendered using fully measured bills of quantities and the contract placed using a JCT 2008 Standard Form.

There are 5 headings that must be addressed within the account (see Table 1):

  1. the original/provisional contract sum;
  2. any omissions of provisional sums and provisional work and any adjustments against these sums;
  3. all additions and omissions as a result of varied work properly instructed by the contract administrator;
  4. all additions and omissions as a result of the issue by the contract administrator of revised drawings and/or specifications resulting in agreed re-measures of quantities; and
  5. the addition of money due as a result of loss and/or expense incurred due to the granting of extensions of time.

Additionally, if the project is large then the effect of fluctuations/increased cost and the effects of any liquidated damages applications must be considered.

 

 

Omit

Add

 

 

£

£

 

Adjustment of preliminaries provisional sums (PS)

 

 

1

a) Omit PS for new incoming electrical main as AI No. 2

5,000.00

 

 

b) Add new electrical intake in accordance with attached quotation and instructed in AI No. 2

 

4,300.00

 

c) Add main contractor's on-costs as declared for special attendance at 5%

 

215.00

2

AI No.3

 

 

 

a) Omit PS for dayworks labour

2,500.00

 

 

b) Omit PS for main contractor's percentage on costs @ 150%

3,750.00

 

 

c) Omit PS for dayworks material

1,000.00

 

 

d) Omit PS for main contractor's percentage on costs @ 20%

200.00

 

 

e) Omit PS for dayworks plan

500.00

 

 

f) Omit PS for main contractors percentage on costs @ 20%

100.00

 

3

Add daywork account as attached (example only)

 

6,850.00

4

Omit general contingency sum - AI 3

25,000.00

 

 

Adjustment of General Provisional Sums

 

 

5

Omit provisional measurement for breaking out any obstructions in the foundations:

5m2 concrete @ £45/m2

225.00

 

 

Add breaking out concrete obstructions as measured on site:

6m2 concrete @ £45/m2

 

270.00

 

Add backfilling void, with MOT type 1 hardcore as directed by clerk of work

6m2 @ £65/m2 – (rate as used elsewhere in tender)

 

390.00

6

Omit provisional sum for mechanical and electrical engineering services as AI No.3

120,000.00

 

7

Add final account for works by Messrs Smith and Taylor Services as attached (example only)

 

137,250.00

 

 

158,275.00

149,275.00

 

 

(149,275.00)

 

 

TOTAL OMIT TO FINAL ACCOUNT MAIN SUMMARY

9,000.00

 

Table 3: Provisional sums and provisional work account

Table 3 shows how within 1 relatively simple section of a final account, there are other 'sub-accounts' which in this example are the Daywork account and the M&E services account.

This situation can be further complicated, especially with regards to the M&E services accounts because there will almost certainly be provisional sums, variations, re-measures and the like, which have to be considered within this sub-account.

This again reinforces the need to adopt best practice and ensure the account is commenced as early as possible and the compilation of information is clearly ordered and structured.